It's only 12 days until the open house for the Parade. It looks like there's so much more to be done but we've been assured that our builders are skilled at making things happen. From last week, we confirmed the damage to the septic system - it was fixed this week. Also, the bad concrete was taken out and replaced this week, as was the bad tile job in the master bath. Next week we tackle the bar, flooring, more tile, landscaping, stone work, paint, plumbing and electronics.
Here's a view of our staircase. Tim and Larry have been working for a couple of days on installing our spindles.
Saturday, September 11, 2010
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment